ONN – Las Vegas Stadium Allegiant Stadium Roof 80 Days Behind Schedule, Oakland Raiders, Oakland A’s News
Vital Vegas, Las Vegas best blog in this blogger’s view, often breaks stories the Las Vegas mainstream media either misses or just doesn’t want to report. In my personal experience I can’t remember when Vital Vegas, the media brand and admitted hobby of of Scott Roeben, has ever been wrong about news it broke. Scott’s not said much about Las Vegas Stadium, so when he does, that is news, in itself.
For example, Scott Roeben got the story of the sale of Rio Las Vegas Hotel before anyone else did. Thus, I and others paid great attention to his tweet on Las Vegas Stadium Allegiant Stadium. This one:
Yikes. Hearing roof at Allegiant Stadium is 80-100 days behind on construction schedule.
Yikes. Hearing roof at Allegiant Stadium is 80-100 days behind on construction schedule.
That formed the main topic for the livestream on Zennie62 on YouTube (click to subscribe please). Note that Vital Vegas did not write that the some aspect of Allegiant Stadium roof construction would be delayed, just that whatever was going on, it would lead to a delay of 80 to 100 days.
That comes as no surprise. The process of building the structure for what is called the ETFE Roof is complicated. Oakland Raiders Construction Manager Don Webb told Rick Velotta of the Las Vegas Review Journal “It’s not just understanding all of the steps that have to be taken, but understanding the sequence that makes the most sense so you’re not painting yourself into a corner. That’s why the schedule has 23,000 tasks on it and they simulate it (the roof installation) on the computer, animate it and run the simulation to see where everything is on any given day.”
Fluxuating temperatures and wind gusts can prove to be the enemy of the Las Vegas Stadium construction process. Just three days ago, Las Vegas played hosts to winds reportedly up to almost 20 mph. That changing pattern in a 2019 Las Vegas weather story that has seen record rains and even snow, makes the process of the reportedly planned, daily lifting of the roof into place high above the stadium floor that much more complicated, and problematic.
“The thermal expansion and contraction of this building will be several inches so there will be a prescribed range of temperatures for those final connections,” Webb told Velotta for the Review Journal. “If it’s not within the tolerances, we will have to wait. That’s why we scheduled the way we did. We had to look ahead and anticipate when this is going to occur. We had to look at historic temperatures and figured out the time of day the final connections should be made.”
Looking at historic temperatures in Las Vegas, and considering how crazy the weather has been, it’s no wonder there’s a problem at Las Vegas Stadium. Don Webb has said, many times, that the stadium schedule aggressive was difficult to meet. The Raiders should remember that Las Vegas Weather didn’t get the memo that it was supposed to cooperate with the construction timeline.
What does this news mean for the Raiders? Well, looking at where the stadium complex is now, and considering that it’s now October 4th, it’s hard to see how it’s going to be completely ready to be open in less than one year. The forecast expressed at Zennie62Media has always been October 31, 2020. I see no reason to back off that.
If that date of opening comes to pass, the Raiders may wind up playing at the Oakland Coliseum yet again in 2020.
Stay tuned.
Note from Oakland News Now Technical: this video-blog post shows the full and live operation of the latest updated version of an experimental Zennie62Media mobile media video-blogging system network that was launched June 2018. This is a major part of Zennie62Media’s new and innovative approach to the production of news media. The uploaded video is from a vlogger with the Zennie62 on YouTube Partner Channel, then uploaded to and formatted automatically at the Oakland News Now site and Zennie62-owned social media pages. The overall objective is smartphone-enabled, real-time, on the scene reporting of news, interviews, observations, and happenings anywhere in the World and within seconds and not hours. Now, news is reported with a smartphone: no heavy and expensive cameras or even a laptop are necessary. The secondary objective is faster, and very inexpensive media production and distribution. We have found there is a disconnect between post length and time to product and revenue generated. With this, the problem is far less, though by no means solved. Zennie62Media is constantly working to improve the system network coding and seeks interested content and media technology partners.
Zennie Abraham is Zennie62Media, Inc. CEO and Zenophon Abraham Zennie62 YouTube Channel vlogger, and creator of Oakland News Now and Zennie62Media's 100-blog network. He's covered the NFL, San Diego Comic Con, The Night of 100 Stars Oscars Party, The NFL Draft, and CES Las Vegas annually more than 10 years. He created Oakland's first true blog, Oakland Focus, and Oakland's first YouTube Partner Channel. Zennie also holds the distinction of forming Oakland's only bid to host the NFL's Super Bowl Game, in 2000 for the 2005 game that Jacksonville won the right to host. He's also the founder of Sports Business Simulations and the creator of The Oakland Baseball Simworld and XFL Simworld.
OaklandNewsNow.com, Oakland News Now, Oakland News Right Now, Oakland-News-Now.com, oakland news today, oakland today news, @OaklandNewsNow, Zennie Abraham, Zennie, Oakland studio apartments, #OaklandNewsNow, #OaklandForever, Oakland Apartments for Rent, oaklandnewsblog.com, Women for America First, Amy Kremer , Swyft Filings, StreamYard, Bowie Refined Coal, Higher Heights, South Dakota Gov. Kristi Noem, political power, Black women, Rio California, Preservation Park, Old Oakland, Oakland City Center, jill biden west wing, Ginele Harris, Brendon Woods, Alameda County Public Defender, Colleen Quigley Olympian FSU, beyond bright led light as seen on tv, NFL Combine 2021, virtual event, current news, oakland ca, china town, Lamar Jackson Ravens QB, Zennie62Media, Inc., influencer marketing, CEO Zenophon Abraham AKA Zennie62 YouTube Zennie62.com Oakland News Now Commentary Vlog YouTube Partner, Oakland California blogger / vlogger Zennie Abraham @ZennieAbraham . Hire @Zennie62Media, Inc to tell your story.
sarah isgur wikipedia, daniel kalb, search engine optimization, bank of america cares act, grand lake theater marquee, john landgraf fx, benji lock shark tank, oscar grant plaza, las vegas raiders stadium live cam, Derek Carr, Vincent Bonsignore, Deshaun Watson, Fly Me To The Moon, Oakland's Alley, miss a beat, going virtual, Taiwan based HTC Corp, arlene guzman todd texts , amy guzman todd, Bay Area shootings Today, Mount Zion Missionary Baptist Church, song requests, Zennie62Media uses smartphones enabling our 98-blog network, John McWhorter, specially-made blogs, corporate, loop capital chicago, Superspreader, March to Save America, Trump rally, Julie Jenkins Fancelli, Publix Super Markets, Breitbart News Network, George Jenkins, laura ehlen bodybuilder, john siegel kentucky, Eric Bieniemy, Super Bowl LV, Byron Leftwich, Tampa Bay Bucs, Super Bowl Halftime Show, publicity consultant, wisconsin capitol protest, raiders mark davis sheldon adelson, female muscle, website, ZENNIE62MEDIA Hoodie, social media platforms covering politics, Las Vegas Sands, Sheldon Adelson, Venetian, League of Women Voters, Samantha Power usaid, The Oakland Protocol, gary levin coal, richmond, Levin-Richmond Terminal, Richmond City Council, Oakland City Councilmember Rebecca Kaplan At Large Speech, Oakland City Council 2021 Inauguration, Western Bit Acquistion LLC, Terminal Group, players, DUI, star trek the motion picture, Spock, Nimoy, Captain Kirk, Lt. Uhura, Sulu, Chekov, news, sports, and tech, streamyard, ZOOM, www.cnn.com, ghirardelli san francisco, OAL Oakland Athletic League, @Oaklandcitynews, John Burris Law, police brutality cases, former Oakland Army Base site, Oakland Police federal monitor, housing for homeless people, cost of natural gas building vs electric, Oakland CARES fund, Berkeley City Councilmember, Alameda City Councilmember, San Leandro City Councilmember, Oakland City Councilmember, Oakland City Council, North Oakland, East Oakland, Montclair, Adams Point, Uptown Oakland food culture, Oakland City, Oakland Cemetery, Oakland crime, Oakland directions, Oakland airport, Oakland, California ghetto, Oakland, California Map, Oakland Raiders, Oakland City Hall Plaza, East Oakland, Jack London Square, The Alley Cat Bar, Golden State Warriors, Chase Center, Bob Myers, Joe Lacob, Peter Guber, NBC Bay Area, Council-Member, Councilmember, Council President, Mayor of Oakland, Public-Safety, Affordable Housing, BBQ Becky Dr. Jennifer Schulte , Jogger Joe Henry Sintay, Oakland crime news, Chauncey Bailey, Bank of America loans, COVID-19 updates, homeless news, SF Bay Area news, Martuni's Piano Bar SF, Paul Hlebcar, Jackie Simpkins, Oakland artists, Jeff Loeb, @breakingnewsbayarea, Emeryville, Atlanta news, Chevron Ecuador, Steven Donziger, Fayetteville GA news, @FayettevilleGA Fayette County Georgia, San Francisco news, San Jose news. Also, David Rubin Academy Awards, The Oscars ceremony ,Tom Hanks, Skyline High School, Oakland Sports, Oakland Panthers, Oakland Coliseum, Honda of Oakland, Oakland Arena, Oakland Raiders, Las Vegas Raiders, Las Vegas Stadium Construction, Allegiant Stadium, Las Vegas Stadium Authority, NBA, NFL, NFL Draft, NFL Combine, CES Las Vegas tech, San Diego Comic Con sci-fi. @GrandLakeTheater @LasVegasHotels, Penny Dreadful City of Angels, Academy of Motion Picture Arts and Sciences, AMPAS
RussianMuscleQueen, Zennie62Media, content development, online reputation management clients, side show cars, david perdue stock trades, Oakland landlords, Owen Thomas, Valleywag, Emilio Garcia-Ruiz, Audrey Cooper, Emma Silvers, culture, Lindsay Graham, Mitch McConnell, Ted Cruz, Stop the Steal, Jurell Snyder shooting, legendary, godzilla vs. kong, king kong, mechagodzilla, claudia conway, lionel richie, American Idol, Alex Marlow, Kroeber Hall, Alfred Louis Kroeber, Tacoma Police runover, Avril Haines, benjilock by hampton, Laray J. Benton, Best Skate Boarding Spot in Oakland, illegal dumping, soul disney pixar oakland, Jamie Foxx, Edna Brewer Middle School, Brewer Jazz Band, rick gates trump interview, would be oakland coal baron bankruptcy, Berkeley Adeline Corridor Plan, barbara lee congresswoman news, Insight Terminal Solutions, @InsightTerminalSolutions and The Oakland Bulk and Oversized Terminal, with California Capital Investment Group Managing Partner Phillip Phil Tagami @PhilTagami co-developer, JMB Capital Partners, @JohnSiegel, John Siegel as ITS CEO exposing coal and Oakland fake news, Greg Minor oakland, Pat Cashman, Humanist Hall, David Oertel, lyft commercial kaplan, uber tax, lyft driver. Zennie62 has helped Maria Ayerdi Kaplan @MariaAyerdiKaplan, developer of Salesforce Transit Center in San Francisco, Kofi Bonner Five Points, San Francisco Shipyard, and Flowsent capture the Oakland Cannabis Delivery Dispensary @OaklandCannabis market with fitness model female bodybuilder Laura Ehlen and weedmaps help. We’ve partnered with The Berkeley Post, CoLoursTV, CNN, 48Hills, TechCrunch, Quicken Loans, Bedrock Development, SFist, YouTube, Google, NBC, Vice, Oakland Post / Post News Group, Landis PR, and other media organizations. Competition: The SF Chronicle, San Francisco Chronicle, Streetsblog San Francisco, SFStreetsBlog.org, San Francisco Business Times, Bizjournals.com, NY Times, Salt Lake Tribune, LA Times, Los Angeles Times, Daily Californian, KQED, KALX, KPIX, KRON, KTVU, Las Vegas Review Journal, News-Democrat, East Bay Express, Oakland Tribune, Oakland Voices, The Mercury News, AJC, Atlanta Journal Constitution, Hoodline, SF Examiner, Sports Illustrated, Sanpete Messenger, The Citizen, The Athletic, The Montclarion, Marin Independent-Journal
Zennie62 interviews celebrities, Congresswoman Barbara Lee, Latino Senator in California, Senator Alex Padilla, Joe Montana, Sammy Watkins, United Airlines, Flight 328, Honolulu, Le'Veon Bell, Ronnie Lott, Marin County, Supervisor Damon Connolly, Mill Valley, Carole Quan, Charles Woodson, Intercept, Vincent Jackson, Mr. Super Bowl Peter O’Reilly , Jim Steeg, Frank Supovitz, Don Weiss, LBJ Enterprises LLC, Julie Buehler, Cafe 817,Woody's Cafe, Edward Lozzi publicist, Anja Crotts, Marin County Supervisor Damon Connolly, town, digial LED screen, President pro tempore, California State Senate, Don Perata, Jean Quan, rank choice voting, Ron Dellums, Robert Bobb, Omri Aflalo, John Cahil, Darrin Ballon, natural gas banned in new buildings, town revival restaurant, Elegy for Tony Hsieh, Lars Frykman, London, David Squires, Aldon Smith NFL, scott haggerty, Jay Glazer, Bill Boyd, Arizona Cardinals QB Kyler Murray, Garrett Gilbert Cowboys, Megan Avalon buffed, Kortney Olson female bodybuilder, Sarah Isgur Trump, Spin1038, Dak Prescott, Charles Woodson, Raiders Owner Mark Davis net worth, Raider Legend Raymond Chester, Brianna Noble, Vince Vaughn,
Chris Evert, Serena Williams, Naomi Osaka, Austrialian Open Tennis, 2425 Valdez, Nook on Valdez, Apartments.com, DeMaurice Smith, NFLPA, systemic racism, Ainsley Earhardt, driving while intoxicated, DUI, Fox News, Fox and Friends, Donald Trump Jr. Partying Video, Oakland African American NFL Expansion Team Seeks NFL Expansion Franchise, Malin Akerman,Jon Favreau, Earline Patricia Yerger, Hyundai Kona, Enterprise Rental Car, Tom Guerino Of PG&E, Dr. Shirley Weber, Mike Silver, Aaron Rogers, Paul Guenther, Reggie McKenzie, Ed Goines, general counsel, Raiders Defensive Coordinator, Reid A Seino, Salem Oregon, coolest reptile pad in oakland, Derek Mason Vanderbilt, Marcus Mariota, Oregon, Justin Herbert, scrambler, Vikas Tandon, interceptions, Josh Jacobs, Kristin Davis, Jennifer Dyer, Kiaran Sim, Yappa World Inc, dave stewart oakland a's, Oakland Chamber of Commerce, Melissa Carone, Port of Oakland Import, Karen Bass, Victoria Vzvodnaya, Theresa Ivancik, Muscle Girl, Girl Fitness, cunningham affair, USFDA, Willie Brown, Hala Hijazi, Jason Bateman, walter williams economist, warriors community court, tagami not backing down, skyline school oakland, westlake school oakland, Jim Caldwell, Matt Patricia, Kristen Bell, Jean Reno, .NY Giants Owner John Mara, @SportsTalk Tony Bruno, Sports Agent Leigh Steinberg, net worth, Oakland City Charter, vloggers, Mason Riggs, Richard Haick, Fox News Tucker Carlson, Henry Sintay Oakland’s “Jogger Joe”, Alameda Labor Council, Cam Newton, Danny Vitale, Henry Ruggs, Cee Dee Lamb, Jerry Jeudy, Chris Cabott, sports academy, NFL Commissioner Roger Goodell, California Governor Gavin Newsom, Tanis Parenteau, Scott Kidd, Actors Richard Dreyfuss, Jim Kelly and John Saxon of Enter The Dragon, Lou Ferrigno, Lindsey Vonn hot legs, Blake Neely, SDCC’s David Glanzer, Publicist Edward Lozzi. Topics like Oakland Apartment rents, Essex Oakland, Fortress Investments, Forest City Development Housing, Lennar Corporation, Oakland City Center, 1200 Lakeshore, Perch Coffee, Haddon Hill, 565 Bellevue, Lake Chalet, Room 389, Golden Bear, Jerry Figone, Johnny Love Metheny, Lakeshore Business District, Eastmont Mall, WordPress, CVS Mail Order and Pharmacy, Kaiser Permanente, Rosa's Home Cooking Restaurant, Oakland Community Kitchens, Lukas Oakland, Maria Alderete, The Studio Cafe, Black Lives Matter, iron ore and coal, John Muir, Oakland hangman noose problem, Oakland NFL Football, Rayzin Schnitzer 11th Street Diner Miami, George Floyd Protests,
Jason Matthew Smith, Cupcake, Star Trek, Jared Leland Gore, stand-in, West Oakland, james ivory berkeley, merchant ivory, Women of The Black Panther Party, Oakland City Charter, Atrium Health Navicent, James Jackson, Delvecchio Finley, Alameda Health System, Ashlyn Webb, 801 Longridge Rd Oakland, @OaklandCityCouncil, Vice President Harris, global content, 25th Amendment,Porsche Taycan Turbo S, Carrie J. Judge, Fingerprint Door Lock, Musician Kev Choice, Cam Newton, Leo Carson, bust sculpter, Andrew Frank, Karv Communications, Anthony Booger McFarlane, armed robbery, anari sengbe, Victor sengbe, chadwick boseman funeral, Jackie Simpkins, Owner of The Alley, Skywalker Sound Marin, Clifton Hall, Oakland Rockridge Housing, Oakland Athletics Liam Hendriks, Dave Stewart, Tribune Tower, Tagami Vision, Charlie Pine, CES 2021 Innovation Award, Oakland 2017 Race and Gender Disparities Study, nfl fall league meeting, NFL on Fox, owners meeting, Vloggercon 2006, josh wolf, International Academy of Web Television, rocketboom, Jessamyn Sabbag, Oakland Rising, progressive organization
Deadline to apply is, arlene guzman cal cunningham, 2020, Broadway and Franklin Streets, California Condo conversion, Saudi Arabia, Mid East Blog, Aston Martin, Highland Hospital, The Public Investment Fund, subletting, Al vs The NFL, Amy Trask, The Mauritanian, Danica Patrick, Aaron Rogers, Ben Volavola, Shailene Woodley, sublet, Oakland United Beerworks, Danger Zone Weizenbock, odell beckham jr, arlene guzman todd, vlogging, amanda congdon, Thomas Espinosa, Oakland Public Ethics Commission, Anthony Harbaugh, Bliss Belly Kitchen, Kay Madati, vlog show, comedy actor, Flash, h264 codec, Carron Phillips Deadspin Jameis Winston, james wiseman warriors, jay blias espn, Mountain View, CA, London, England, Moscow, Russia, Raphael Warnock, Senator Kelly Loeffler, pinewood atlanta, mark dice, White Privilege Tax, Media Analyst, Ronald Jones Bucs, Cal football, UCLA, USC, Stanford, blacks in tech, Tackett Bartlett LLP, Berkeley Bowl, Peets Coffee, @TackettBartlettLLP, Jameis Winston bucs saints florida state, East Bay Regional Park District, Berkeley City Auditor, Judge John Sutter Regional Shoreline park, Pinewood Studios Atlanta, Jeff Miller, Joceyln Moore, Derek Carr, Marcus Mariota, Regina Jackson, Barry Donelan, Deborah Matthews, Yanqing Ye, UC Berkeley, NFL Owners Meeting, NFL Annual Meeting, Eli Lilly Coronavirus COVID-19 vacine, Summit Bank Oakland, SIFF, Sonoma International Film Festival, Bank of America, Oakland protestors arrested, Juneteenth Rally, Len Raphael, Southern Evangelical Seminary, Richard Land, Kyle Rittenhouse, Jacob Blake, Kenosha, Carroll Fife, Mike Hutchinson Oakland, Alison Roessler, Jane Greenberg, Albert Dicruttalo, Brie Larson, Mayor Of Chicago, Orlando Martinez, Robert F. Smith, supreme court justice ruth bader ginsberg, coalition for police accountability, Youth vs. Apocalypse, Atlanta Mayor Keisha Lance Bottoms, Georgia Governor Brian Kemp, Kate Harrison, Joe Burrow, Cheryl Davila, Mayor Jesse Arreguin, Lori, Droste, Stephanie Walton, Tri Ngo, berkeley marina, berkeley city, Jeff Bezos, Amazon, The Washington Post, Washington Redskins, Washington NFL Football Team, NFL Football Team, Barbara Leslie, Yui Hay Lee, Andreas Cluver, White Journalists, Blacks In Media, Alana Nguyen SFGate, Morgan Bach, Derr & Isbell Construction, Merrill Iron & Steel, Inc
WebiMax, Gadook, VJG Interactive, LocalEdge, Digital Firefly Marketing, GreyBox Creative, Igniyte, Reputation Rhino, Netmark, Outspoken Media, SEOValley, WebpageFX, NetReputati, san francisco reputation management, atlanta reputation management, los angeles reputation management, Indeed, airbnb, pinterest, credit karma, Joseph Le Conte, southwest airlines, mcdonalds, united airlines, Peel-A-Pound Soup, drudge report, astros, 49ers, frontier airlines, tractor supply, UC Berkeley ranking, warriors, alaska airlines, buffalo wild wings, horoscope, shein, raiders, uhaul, ted bundy, nba finals, michaels coupon, Tua Tagovailoa, cheesecake factory, golden state warriors, kevin durant, realtor com, stephen curry, walgreens photo, drudge, facebook sign in, funny memes, hbo go, hbo now, oakland raiders, Pacific Merchant Shipping Association, oakland national night out, vistaprint, braves, san francisco 49ers, monday night football, newegg, travis scott, zion williamson, kohls coupons, lands end, nancy pelosi, kohls coupon, hotwire, Kamala Harris, Joe Biden, Patrick Mahomes, mark davis raiders wife, al davis,mark davis net worth, mark davis van, mark davis raiders haircut, mark davis car, mark davis minivan, raiders owner net worth, harry potter, giants, craigslist sf, craig newmark, vic beasley, california earthquake, boston weather, las vegas weather, Eric Metz, sf giants, san francisco weather, san francisco, los angeles weather, lord and taylor, star wars, star wars episode, star trek, star trek discovery, william shatner, ermal allen cowboys, Tom Landry, Jerry Jones, Gil Brandt, Tex Schramm, #Yayarearevolution, zinni.com, zenni.com, leonard nimoy, j.j.abrams, jimmy garoppolo, hawaiian airlines, detective pikachu, clint eastwood, bed bath and beyond coupon, abercrombie, pewdiepie, sfgate, sc lottery, berkeley school, san diego weather, san antonio weather, southwest flights, pikachu, golden state, myatt, just mercy, french open, colourpop, cam newton, anna kendrick, actor, sexual harrassment, klay thompson, harbor freight coupon, robin williams, protest in Oakland, portland protest, Berkeley protest, Chicago protest, LA protest, berkeley university
Wanda Johnson, Oscar Grant, Anthony Pirone, Yes We Can Obama, Judge Alison M. Tucher, Iris Canada Case, Maria Muldaur, Phil Spector died, lana clarkson, essential workers, Super Bowl Opening Night, Saudi Arabia, 24hrs (rapper), A-Plus (rapper) , Askari X, Baby DC , Bambu (rapper) , Ant Banks, Sway Calloway , Clyde Carson , Casual (rapper), Del the Funky Homosapien , Politico, Daveed Diggs , Dru Down, E-A-Ski, G-Eazy , The Grouch (rapper) , Guapdad 4000, Jel, Kafani , Keak da Sneak, Lateef the Truthspeaker , Damian Lillard, Mac Dre , Mistah F.A.B., Numskull, Opio, Pep Love, Phesto , Philthy Rich, R. Prophet, Richie Rich (rapper), Boots Riley, Seagram (rapper) , Shady Nate, J. Stalin, Tajai, V-Nasty, Yukmouth, Four Points By Sheraton New York City, Aria Las Vegas, Ballys Las Vegas, Bellagio Las Vegas, Marriott Oakland, Oakland Youth Chorus, Marriott SF, Grand Hyatt San Francisco, Best Western Las Vegas, Caesars Palace, Circus Circus Las Vegas, Cosmopolitan Las Vegas, Beverly Hills Hotel, Beverly Hilton, Delano Las Vegas, Encore Las Vegas, Excalibur Las Vegas, Flamingo Las Vegas, Four Seasons Las Vegas, Harrahs Las Vegas, Linq Las Vegas, Luxor Las Vegas, Mandalay Bay Las Vegas, MGM Grand Las Vegas, Mandarin Oriental, Mirage Las Vegas, Monte Carlo Las Vegas, New York New York Las Vegas, Paris Las Vegas, Palazzo Las Vegas, Planet Hollywood Las Vegas, Stratosphere Las Vegas, Wynn Las Vegas, Venetian Las Vegas, Vdara Las Vegas, Circa Las Vegas, D Hotel Las Vegas
Howard Terminal Ballpark, Seattle protest, Happy New Year 2021, Pink Floyd In Concert, oakland fireworks, Nashville Downtown Explosion, “Designated Survivor” At Inauguration, Noble Prize, Gamerholic, system dynamics modeling language, air scrubbing and HEPA Filters, Justin Wilcox,Dwayne Haskins released, David Shaw, Stanford Football, Melanie Merkosky, Continuum, CARES Act, Stanford at Cal 123rd Big Game, Bill Musgrave, Justin Wilcox, David Shaw, the informal economy, gross domestic product, LonelyGirl15, Bree, Renetto, vlog life, business finance, portland weather, phoenix weather, Oakland LGBTQ Center, Lakeshore Ave, malcolm miller oakland police cop, rick gates trump interview, small business administration, PPP, north carolina, macbook, how, bath and body works coupon, League of Women Voters of Berkeley, Albany, Emeryville, The Pandemic, community organizer, berkeley coronavirus,, sports events,googleflights, daytona 500, daily horoscope, ashton kutcher, mask, Economic Stimulus, andrew luck, alamo drafthouse, 49ers schedule, trump tweets, MyoKardia, chadwick boseman, colon cancer, Black Panther, MARVEL Entertainment, Disney, thanksgiving,How to, What is, How do I, What do I, Who is? , Electronic Frontier Foundation, Howard Terminal Ballpark, Natalie Silver, Pass It On, Barbara Leslie, Yui Hay Lee, Andreas Cluver, White Journalists, Blacks In Media, David Rubin, Frances Dinkelspiel, Alana Nguyen SFGate, Cat Brooks, Anti Police-Terror Project, Mountain Mike’s Pizza, Glenview, Restorative Justice, School Crossing Guards, berkeley philosophy
Comedy Central Roast Battle, Shawn Felipe, NBC, Festive Company, Latham Square, Breonna Taylor bust statue, vaccines, SARS-CoV-2, D614G, mutation, vandalism, Natoinal Lampoon, Ben Feldman, SF Weekly's Comic To Watch,Leighann Lord, Matt Kirshen, Last Comic Standing Finalist, Subhah Agarwal, MTV2, Comedy Central,Anna Valenzuela, Samson Koletkar, BookMyShow, 10 Best Indian-Origin Comedians of the Last Decade,Ira Summer, US Comedy Contest Finalist, Bosch ,Canon,,Caterpillar ,HERE ,Technologies ,Hisense ,Indy ,Autonomous , Alex Padilla, First Latinx Senator, Indianapolis Motor Speedway ,Intel Mobileye, Kohler , LG Electronics, Magna International, Mercedes-Benz, OMRON Healthcare, Panasonic, Philips, Samsung Electronics, Schneider Electric, Skyworth, Sony, Verizon, Taiwan Tech Arena, Bill Belichick ,New England Patriots, Sean Payton, New Orleans Saints, Andy Reid, Kansas City Chiefs , John Harbaugh, Baltimore Ravens, Sean McVay, Los Angeles Rams, Mike Tomlin, Pittsburgh Steelers, Kyle Shanahan, San Francisco 49ers, Pete Carroll, Seattle Seahawks, Bruce Arians, Tampa Bay Buccaneers, Frank Reich, Indianapolis Colts , Mike Zimmer , Minnesota Vikings , Doug Pederson, Philadelphia Eagles , Mike Vrabel, Tennessee Titans , Sean McDermott, Buffalo Bills , Matt Nagy, Chicago Bears , Kliff Kingsbury, Arizona Cardinals , Zac Taylor, Cincinnati Bengals, Bill O’Brien, Houston Texans, Kevin Stefanski, Cleveland Browns, Ron Rivera, Washington Redskins , Brian Flores, Miami Dolphins , Joe Judge, New York Giants, Mike McCarthy, Dallas Cowboys, Matt Rhule, Carolina Panthers, Jon Gruden, Las Vegas Raiders, Matt LaFleur, Green Bay Packers, Anthony Lynn, Los Angeles Chargers, Vic Fangio, Denver Broncos, Dan Quinn, Atlanta Falcons, Matt Patricia, Detroit Lions, Doug Marrone, Jacksonville Jaguars, Adam Gase, New York Jets
Also Elon Musk, YouTuber , Big Helicopter, Jake Angeli, Jacob Chansley, Trump Protestors, Terrorists, rioters, Ricky Ricardo, Ricky's Sports Theater, Raider Nation, NFL Pro Bowl , Nura Gabbara, Lonnie Murray, Cleveland Hustles, Pat Abraham Yerger, Earline Patricia Yerger, StreamYard, ZOOM, Jitsi, Sunne Wright McPeak, transportation, bullet train, financing debt, Glide Memorial Church SF, Greg McConnell Jobs and Housing Coalition, Oakland Mayor Libby Schaaf @LibbySchaaf, Pamela Price, Councilmember Nikki Fortunato Bas, Dan Kalb of District 1, Loren Taylor, Lynette Gibson McElhaney, Sheng Thao, Noel Gallo, Robert Bobb, Rebecca Kaplan, Larry Reid, Tech Entrepreneur Sarah Lacy, Personal Trainer Megan Avalon Buffed Barbie, Social Media Pioneer Marc Canter, Blake Lindsley, Beth Schnitzer, Spritz Marketing, Eleanor Wikstrom, SF Mayor London Breed, Scott McKibben, CA Assemblymember Buffy Wicks, Schools Superintendent Tony Thurmond, Berkeley Councilmember Ben Bartlett @BenBartlett, Raiders Charles Woodson, 49ers Jerry Rice, Grand Lake Theater Oakland Owner Allan Michaan, Gary Meyer Telluride, Eat Drink Films, C.J. Hirschfeld, Shaun Tai , BRIDGEGOOD, Oakland Digital, Issac Kos-Reed, Salsa-By-The-Lake, AMC Cinemark TinselTown, Children's Fairyland, Irvine City Manager John Russo, Guy Fieri, Oakland CAO Edward Reiskin, Raiders Coach Jon Gruden Running Back Josh Jacobs, Stanford HC David Shaw, Tri Ngo, Atlanta Falcons Coach Dan Quinn, Michael Mina, NFL Draft Mr. Irrelevant Head Melanie Fitch, Paul Satala. Eva Crawford, Lauren Weisheit, Subscribe to Zennie Abraham’s @Zennie62 YouTube Channel, today!
ZennieAbraham is Zennie62Media, Inc. CEO AKA Zenophon Abraham Zennie62 YouTube Channel, Zennie62.com, newsbreak.com, nydailynews.com , allhiphop.com, Wonderwall, Eurweb.com, The Source, Oakland CA News, Oakland, California, Oakland vlogger, Oakland News Now Today Blog – SF Bay Area Daily, WordPress user, full stack developer, online reputation management digital marketing expert, SEO, digital media guy, economic development , personal online content , management reputation services, east bay democratic club follower, Oakland Black Panther Elaine Brown, super car stats dude, CES Las Vegas, tech news blog, OaklandNewsOnline.com, OaklandNewsNow.com, OaklandNewsToday.com, Oakland Post, Oaklandpostonline.com, Oakland restaurant foodie fan, Oakland Mayor's Office - Oakland City Council veteran, NBA Blogger, NFL Blogger, Pro Sports Blogger,Super Bowl Bid Expert, Skyline High School Oakland grad, Jeff Katzenberg Quibi App tech commenter, Texas-Arlington Alum, UC Berkeley DCRP Alum, Cal Alumni Board of Directors Alum, Oakland Raiders, The Athletic, Sports Illustrated, Leigh Steinberg, Julia Faron, Chris Cabbot, Cosmo DeNicola, Leigh Steinberg Super Bowl Party, New York 21 Club, Las Vegas Raiders, Dallas Cowboys, NFL, NFL Draft Draftnik, Roger Goodell, Adam Silver NBA, media blogger, social media pioneer, college football news, coder, football strategy junkie, Oakland elections news, zenni, zenni glasses, optical, eyewear, Maria Ayerdi Kaplan, Salesforce Transit Center, Oakland Mayor Libby Schaaf, California Governor Gavin Newsom, Councilmember Noel Gallo, Sheng Thao, Rebecca Kaplan, cheryl davila, Rick Gates Trump, Ben Bartlett Berkeley, Oakland City Attorney Barbara Parker, Treva Reid, Amy Cooper,
Chris Cooper, Mary J Blige, jaquar wright, sean puffy combs, Comedy Oakland, neoliberal, Annalee Allen, Barack Obama, wicked game book, deputy campaign manager, richard w gates jr, george papadopoulos, roger stone, michael cohen, White House Senior Staff, Darrell Williams, Chicago, Murray Energy, International Terminal Solutions, Sanpete County Utah, John Siegel, Autumn Wind Lending, General Partner, Avenue Of The Stars, LLC, Flowsent, Oakland Bulk and Oversized Terminal, OBOT, Las Vegas visitor, Lam Research Corporation, YouTube Partner, friend of Mike Silver, Leslie Silver, Pass It Down podcast, Phil Tagami, Phil Gates, oakland harborside, Nancy Sidebotham, Henry Gardner, Davey D Cook, Ray Bobbitt, Bill Duffy, Robert Bobb, Alan Dones, Loop Capital, Shaun Tai BRIDGEGOOD, Robert G Schock, Barbara Schaaf, Marc Canter, Patricia Yerger Mom, Harrison Chestang, KPOO, Gary Schapiro, Zenophon Abraham Sr. Dad, Vloggerheads.com member, Vloggercon attendee, The Alley Cat Bar regular, Grand Lake Theater marquee fan, United Airlines flier, Walt Disney World lover, System Dynamics consultant, Fluidigm Corporation, Eddie Van Halen, Run DMC, Rolling Stones, Old School Rap fan, Star Trek Trekker, movies buff, San Diego Comic Con Press regular, female bodybuilder fan, Wonder Woman, melissa benoist, Supergirl, Singer Associates, Spritz Marketing SF, Oakland and San Francisco Planning follower,
Atlanta Georgia, Atlanta Falcons, Fayette County, Fayetteville observer, Tiger Woods Masters, Thomas Bonk, Robin Carr, Jamaican Cuisine, Tibor Lacey Zenni.com name, Zennie62 YouTube Partner, Hollywood, Oakland California blogger / vlogger hire @Zennie62Media, Inc to tell your story.